Healthcare · operations and process · multinational · GE · 2018–19
Delivery was holding up the close
Situation
MRI and ultrasound followed the same workflow, with the same people, despite the differences in volume and complexity.
Open caseClose case
Starting point
47
After
4
days, medical equipment delivery lead time
Evidence
MRI is large equipment, sold in few units, at millions of reais each. Ultrasound is portable, sold in many units, at around R$160,000 each.
Reading
The flow treated every order the same and checked the same thing more than once.
Decision
The workflow was split by volume and complexity, with less sales and finance red tape.
The takeaway: The bottleneck is rarely in selling more. It's usually in what happens after the yes.
Open the case readingHealthcare · costs and taxes · multinational · GE · 2010–11
The most expensive problem isn't always the one in the report
Situation
Imported parts were classified incorrectly, and items with no domestic production were still subject to taxes that could be reviewed.
Open caseClose case
Over US$20M
a year in tax savings
Evidence
Accessories that were already exempt were being treated as IT items, taxed at over 18%.
Reading
Tax on parts was treated as a given. Nobody reviewed the classification after the item was set up, so the error repeated with every import.
Decision
The tax classification was corrected, and a petition was filed with Brazil's trade ministry (MDIC) to exempt or reduce the tax on parts with no domestic production.
The takeaway: Before you cut costs, ask which cost nobody has ever questioned.
Open the case readingHealthcare · sales and revenue forecasting · multinational · GE · 2015–18
Revenue forecasting from a single source
Situation
Sales, logistics and finance needed to work from a single view of the revenue forecast.
Open caseClose case
US$144M
in annual pipeline under the commercial operations I led at GE in Latin America
Evidence
Sales, logistics and finance each showed up with their own spreadsheet and their own forecast, and the meeting started with which number was right. The forecast lived in spreadsheets and email; Salesforce wasn't the source anyone used to decide.
Reading
There was no single source of data and no fixed cadence for the departments to decide together. Without that, each one optimized its own number.
Decision
A weekly and monthly revenue operating rhythm, set up with the business line CEO, brought the three departments together, with Salesforce as the single source of data.
The takeaway: If every department has its own spreadsheet, nobody knows which number is right.
Open the case readingHealthcare · after-sales and services · multinational · GE · 2011–15
Every hard case cost a trip
Situation
When the field engineer couldn't solve it, a senior engineer had to travel to the customer.
Open caseClose case
Starting point
1
After
25
cases resolved per week, remote support capacity
Evidence
Every escalated case meant a trip for a senior engineer: travel cost, hours on the road and one customer served at a time. Some field engineers escalated everything without doing the basic diagnosis.
Reading
Senior expertise only reached the customer if the engineer went on site, and escalation had no filter. Headcount was fine; the bottleneck was the service model.
Decision
I built the region's first remote support center end to end: remote connectivity to the equipment, a new escalation process and a dedicated team. Senior engineers started working cases remotely and freed up time to work with the factories and global teams.
Result
Escalated cases went from more than 18 days to 2 days on average, and NPS (the customer recommendation score) rose 20 points.
The takeaway: If your best technician spends the day on the road, only one customer gets help at a time.
Open the case readingConstruction · quoting and sales operations · New Telhas · since 2021
Quotes took two days to go out
Situation
Quote requests waited 2 days for an answer.
Open caseClose case
Starting point
2 days
After
same day
for a quote to go out
Evidence
The technical calculation for each quote depended on one person.
Reading
The bottleneck was one person, not the volume of requests.
Decision
Fix quoting before chasing more requests.
Result
Quotes started going out the same day. Revenue went from around R$15,000 to over R$1 million a month; that growth came from Novamedia's marketing work.
Healthcare · after-sales and services · multinational · GE · 2011–15
Repairs crossed an ocean
Situation
Life-support equipment and ultrasound transducers were shipped for repair to factories in 7 countries. Freight was expensive and the customer waited.
Open caseClose case
Starting point
90
After
15
days from repair shipment to return to the customer
Evidence
The equipment went for repair to factories in 7 countries, from the United States to South Korea. To decide, I also ran a market study: customers, competitors and demand for the service.
Reading
After-sales was treated as a cost center, not as part of the next sale, and repair capability sat in the factories, far from the customer. So nobody questioned shipping repairs abroad.
Decision
I built Latin America's first Repair Center in Barueri end to end, using two GE models: the repair center in Jupiter, Florida, and the transducer repair center in Golden, Colorado. From the business case and the market study to the site selection, hiring the team, buying the equipment, the commercial offers and the warranty reserves.
The takeaway: Run after-sales like a business, with an owner, a P&L and a customer, and it starts driving repeat business.
Open the case readingTechnology · data and e-commerce · multinational · Samsung · 2019–21
E-commerce as a black box
Situation
E-commerce was a black box across the region's main sites and marketplaces.
Open caseClose case
3rd place
in Samsung's 2020 Global Innovation Award
Evidence
There was no daily data on how Samsung's and competitors' products showed up on partners' sites and marketplaces: position, price, promotion, availability and page quality. The marketing spend to win visibility in those channels wasn't measured or adjusted.
Reading
Without measuring digital presence every day, tactical decisions by category were made in the dark.
Decision
I came up with and built, leading the teams, a proprietary data solution: daily extraction from sites and marketplaces, the regional Digital Display Share metric and BI dashboards. The metric was tracked every day and rolled out to Europe, India and ASEAN.
The takeaway: What nobody measures every week, nobody manages.
Open the case readingBanking · continuous improvement and efficiency · large company · Itaú Unibanco · 2007–10
An improvement program in the middle of a merger
Situation
The bank was rolling out a Lean Six Sigma program. With the merger of Itaú and Unibanco, the continuous improvement area became Operational Efficiency and took on larger projects that integrated departments.
Open caseClose case
More than
60
Green Belts trained to run improvement projects
Evidence
An external benchmarking study, which I led, for the program rollout.
Reading
The program was seen as the quality team's thing, and the departments didn't feel they owned the projects.
Decision
Build the capability inside the departments: train Green Belts, mentor managers and run Kaizen events.
Result
More than 10 Lean Six Sigma projects in growth, productivity and operational efficiency, more than 30 managers mentored and more than 15 Kaizen events.
The takeaway: If only the specialist can run the improvement, it stops when the specialist walks out the door.