Repairs took 90 days to get back to the customer.
Faulty vital signs monitors, anesthesia machines and ultrasound transducers were shipped for repair to factories in 7 countries. From shipment to return, the customer waited 90 days.
Repairs left Brazil for factories in 7 countries.
Where GE's faulty medical equipment was shipped for repair
Brazil Destinations: United States, Germany, China, Israel, Austria, Norway, South Korea
Method stage: Problem
What looked like the problem
Sending it back to the factory looked like the only option: the equipment is complex, the factory is abroad, and the lead time came with it. There was also talk of speeding up freight and customs clearance, and of stocking more loaner units and transducers. Meanwhile, repairs were expensive for GE and for customers in Brazil.
Method stage: Evidence
What evidence I would look for
By type of equipment: how many units went out for repair, to which factories, what the freight cost and how many days the customer went without the device. To decide whether building repair capability here was worth it, I also ran a market study: customers, competitors and demand for the service.
Method stage: Evidence
What the evidence showed
Life-support equipment went to factories in the United States, Germany, China and Israel. Ultrasound transducers went to the United States, Austria, Norway, Israel, South Korea and China. That was 7 countries, with expensive freight and the customer waiting.
Method stage: Problem
What the real problem was
After-sales was treated as a cost center, not as part of the next sale, and repair capability sat in the factories, far from the customer. So nobody questioned shipping repairs abroad.
Method stage: Decision
What I would decide first
Bring repairs close to the customer. I built the business case and went after the two GE repair centers that served as models, to bring in their technology and know-how: Jupiter, Florida (vital signs monitors, anesthesia, ECG and portable ultrasound), and the transducer repair center in Golden, Colorado. Then I ran the local project end to end: picking the site, hiring and training the team, buying the tools and repair benches, getting the factories to sign off, meeting the quality and regulatory requirements for medical equipment, the rollout, the commercial offers and the warranty reserves. It was like building a local business for GE. That became Latin America's first Repair Center, in Barueri, São Paulo. The time from repair shipment to return to the customer fell from 90 days to 15.
What it looked like
Sending it back to the factory looked like the only option: the equipment is complex, the factory is abroad, and the lead time came with it.
Root cause
After-sales was treated as a cost center, not as part of the next sale, and repair capability sat in the factories, far from the customer.
Decision
Bring repairs close to the customer.
Repair time fell from 90 to 15 days.
Before
90 days
After
15 days
Do this tomorrow
List the 10 items that come back for repair most often and write down, for each one, how many days the customer goes without it and what it costs to ship it out and back. Start with the ones that depend on another country or another company.