The equipment took 47 days to reach the customer.

Delivering medical equipment took about 47 days. A US$20,000 order and a US$2 million order waited in the same line.

A US$20,000 order and a US$2 million order waited in the same line.

Medical equipment delivery time, about 47 days for any order

US$20,000 order

Delivery47 days

US$2 million order

Delivery47 days
Source: GE, medical equipment delivery in Brazil.
01

Method stage: Problem

What looked like the problem

Everyone knew the lead time was about 47 days. Nobody could say where the order sat still.

02

Method stage: Evidence

What evidence I would look for

Where the order goes between the sale and the delivery, who works on it at each step and how long it sits at each one. To see that, I brought sales, finance and operations together for a Kaizen week, and we drew the order's path step by step.

03

Method stage: Evidence

What the evidence showed

Finance, credit approval, customer registration and approval (KYC, the check on who the customer is) and proposal writing were shared areas with no link to what the customer at the end of the line needed. A US$20,000 order, a US$150,000 order and a US$2 million order got the same treatment and the same priority. MRI (few units, each in the millions of reais) and ultrasound (many units, about R$160,000 each) went through the same flow, with the same people. On top of that, several areas checked the same things, in duplicate controls that weren't needed and added days to the process.

04

Method stage: Problem

What the real problem was

The flow treated every order the same and checked the same thing more than once. Without separating volume and complexity, the simple order waited in the same line as the complex one.

No single department explained the 47 days.

Where a medical equipment order stalled between sale and delivery

47 daysfrom sale to delivery

  • Credit

    • same priority for every deal size
  • Proposals

    • no link to what the customer needed
  • Customer setup and KYC

    • rechecks what another team already checked
  • The real cause

    Order flow

    • a US$20,000 order in the US$2 million line
    • the same check in several departments
Source: Order path mapped in a Kaizen week with sales, finance and operations, GE.
05

Method stage: Decision

What I would decide first

Split the flow by volume and complexity, with less sales and finance red tape for the simple order, and cut the repeated checks between areas. That was the Fastlane project: delivery went from about 47 days to 4.

What it looked like

Everyone knew the lead time was about 47 days.

Root cause

The flow treated every order the same and checked the same thing more than once.

Decision

Split the flow by volume and complexity, with less sales and finance red tape for the simple order, and cut the repeated checks between areas.

Delivery fell from about 47 to 4 days.

Before

47 days

After

4 days

Source: Project Fastlane, GE, 2018 to 2019.

Do this tomorrow

Take 10 orders from last month, from the smallest to the largest, and write down how many days each one took from close to delivery. If the smallest took as long as the largest, your flow treats every order the same.